Enon Grove – Permitting and Related Updates

Next Section

Oct 29, 2026

The Enon Grove team has a few updates to share regarding the project website, water upgrades and local permitting.

Updates to Website

We have added a number of new Frequently Asked Questions to our website based on questions submitted by local stakeholders and neighbors. We encourage you to check these out on our FAQs page.

We have also added an aerial rendering of the project with its revised layout, including updated equipment and new positioning within the project site, to the home page.

Water System Upgrades

Tenaska has been working with the Heard County Water Authority (HCWA) to evaluate improvements to the water system that would allow it to reliably supply water to the proposed Enon Grove Generating Station. Tenaska retained Garver, which has worked with HCWA in the recent past and has expertise in water distribution system planning and hydraulic analysis, to evaluate the water system and recommend potential improvements.

Garver identified the need to replace nearly 10 miles of existing 6-inch and 8-inch water lines with 12-inch water main. The improvements would address existing distribution system constraints while increasing the capacity available to serve Enon Grove and improve service to existing HCWA customers.

Tenaska has committed to fund the cost of the water system upgrades as part of the advancement of the Enon Grove project.

Planning Commission

Enon Grove has submitted its applications for rezoning and a Special Use Permit to Heard County. The Planning Commission will review the project at its upcoming meeting on November 2, 2026 at 6:00 PM at the Heard County Administration Building at 201 Park Avenue in Franklin.