We are excited to share some updates about the development of our second power plant in Heard County, the proposed Enon Grove Generating Station.

Changes to Project Site and Layout
As our team has advanced development activities over the past year, we have continued to meet with local leaders and neighbors to refine our plans. Taking into account feedback from these discussions, we acquired some additional land to allow for more buffer between the facility and the closest neighbors. We have also secured direct access to Highway 34 to minimize construction traffic on local roads.

Enon Grove is still planned as a simple-cycle peaking plant, which can start up very quickly and generate electricity when demand is highest, such as during extreme heat, cold or other periods of peak energy use. As currently envisioned, the plant would be able to generate up to 2,000 megawatts (MW) of power.

Further, Tenaska has been in discussions with Heard County Water Authority (HCWA) about the proposed plant’s water needs and potential options to expand the HCWA system for both the plant and other local customers. Assuming Enon Grove advances, upgrades will be funded by Tenaska, which will not only allow for the delivery of water to Enon Grove but also increase the reliability of the water supply for HCWA customers.

Tenaska recently presented these changes to the closest neighbors. If you would like to see the full presentation, please click here.

Progress on Needed Permits
We are actively seeking land use approvals from Heard County. Tenaska submitted applications for rezoning and a Special Use Permit to Heard County last week. These applications will be considered by the Heard County Planning Commission and the Board of Commissioners, most likely in November.

The team also submitted a National Pollutant Discharge Elimination System (NPDES) application to the Georgia Environmental Protection Division (GEPD) for review. This review process for this wastewater discharge permit will take several months.

Updates to our application for a Prevention of Significant Deterioration (PSD) permit, which governs air quality, were submitted to the GEPD as well. The changes reflect the latest project details, including equipment selection.